Battery Storage / ESS Sizing Calculator

Size residential and commercial battery storage systems (ESS), backup duration runtime, inverter kW, and 125% circuit OCPD per NEC Article 706.

NEC edition

Inputs

kWh
%
kW
kW
%

VoltageLab app

Take this toolkit with you on the job

The full VoltageLab electrician app — wire tables, code lookups and job-site calculators offline, on Android and iOS.

⚡ Test your knowledge
NEC Article 220 was renumbered in the 2026 code cycle. What is the new article number?
  • A. Art. 100
  • B. Art. 120
  • C. Art. 200
  • D. Art. 230
💡 NEC 2026 renumbered Article 220 (Branch-Circuit, Feeder, and Service Calculations) to Article 120.
Energy Management Systems were moved from Article 750 to which article in NEC 2026?
  • A. Art. 100
  • B. Art. 125
  • C. Art. 130
  • D. Art. 150
💡 NEC 2026 moved Energy Management Systems from Article 750 to Article 130.
Which NEC standard size overcurrent device comes after 90A?
  • A. 95A
  • B. 100A
  • C. 110A
  • D. 105A
💡 Per NEC §240.6(A), the standard sizes are …90, 100, 110, 125… There is no 95A standard size.

VoltageLab app

Studying for your electrical exam?

Practice NEC exam questions with full explanations and progress tracking, right on your phone.

How it works & the NEC rules behind it

Energy Storage Systems (ESS) are governed by NEC Article 706. Sizing an ESS requires evaluating both energy capacity (total storage in kilowatt-hours, kWh) and power capacity (continuous output in kilowatts, kW), along with code-mandated electrical protection.

Key Sizing Rules under NEC Article 706:

  • 1. Continuous Duty Sizing (§706.30(A)): ESS output circuits are rated for continuous operation. Circuit conductors and overcurrent protection devices (OCPD) must be sized for at least 125% of the maximum continuous current.
  • 2. Usable Energy vs. Nameplate Capacity: Usable capacity equals Nameplate kWh × Depth of Discharge (DoD) (typically 90%–100% for modern Lithium Iron Phosphate LiFePO4 cells).
  • 3. Backup Autonomy Runtime: Calculated as (Usable kWh × Round-Trip Efficiency) ÷ Average Hourly Essential Load (kW).
  • 4. Disconnecting Means (§706.15): A readily accessible, lockable disconnecting means must be provided within sight of the ESS equipment.
  • 5. Interconnection Rules (§705.12 / §706.16): Point of connection to electrical panelboards must comply with the 120% busbar rule or supply-side tap rules.

Formulas & equations

Usable Battery Energy (kWh) = Nameplate Capacity (kWh) × Depth of Discharge (DoD) Backup Runtime (Hours) = (Usable kWh × System Efficiency) ÷ Average Load (kW) Inverter Continuous AC Current = (Continuous kW × 1000) ÷ AC Voltage Min Required ESS Breaker = Inverter Continuous AC Amps × 1.25 (§706.30)

NEC reference table

ESS Model / Capacity Usable kWh Continuous kW Peak Surge kW Min 240V Breaker (125%)
Tesla Powerwall 313.5 kWh11.5 kW18.5 kW60 A
Enphase IQ Battery 5P5.0 kWh3.84 kW7.68 kW20 A
FranklinWH aPower (13.6)13.6 kWh5.0 kW10.0 kW30 A
SolarEdge Home Battery9.7 kWh5.0 kW7.5 kW30 A
Dual Powerwall 3 (2 Units)27.0 kWh23.0 kW37.0 kW125 A

Worked example, step by step

Example: Sizing 13.5 kWh Lithium ESS for Residential Critical Backup

Given: 13.5 kWh Nameplate, 95% DoD, 92% round-trip efficiency, 7.6 kW Inverter @ 240V, average critical backup load = 1.5 kW.

  • 1. Usable Energy: 13.5 kWh × 0.95 = 12.825 kWh.
  • 2. Delivered Energy: 12.825 kWh × 0.92 = 11.80 kWh.
  • 3. Backup Duration: 11.80 kWh ÷ 1.5 kW load = 7.87 Hours continuous runtime.
  • 4. Inverter Output Current: 7,600W ÷ 240V = 31.67 Amps.
  • 5. Conductor / Breaker Sizing (125% §706.30): 31.67A × 1.25 = 39.58 Amps → Install standard 40A Breaker with #8 AWG Copper.

Frequently asked questions

Under NEC §706.30, all energy storage system conductors and overcurrent devices must be sized for 125% of the maximum continuous current output of the inverter or converter, because battery systems can discharge at full power for more than 3 continuous hours during grid outages.

In an AC-coupled system, the battery has its own dedicated bidirectional inverter that connects directly into the AC panelboard. In a DC-coupled system, solar panels and batteries connect directly to a single hybrid DC inverter, sharing one connection to the home AC service.